3 Calculation Of Machine Rates
31 introduction the unit cost of logging or road construction is essentially derived by dividing cost by production in its simplest case if you rented a tractor with operator for 60 per hour including all fuel and other costs and you excavated 100 cubic meters per hour your unit cost for excavation would be 060 per cubic meter